Service announcements

  • Status of Campus Elevators

    Goodman School of Business Elevator #1 (east) is out of service. Elevator #2 (west) is available as an alternate.

     

    Categories: Announcements

  • Construction update – Goodman School of Business – September 24 – 28.

    As part of the Goodman School of Business expansion project, the following work is scheduled to start from Monday, September 24 to Friday, September 28.

    Existing Building

    Level 400 North

    • drywall bulkheads and grid ceilings progressing
    • electrical rough-in progressing
    • sprinkler  rough-in underway
    • control wiring progressing

    Exterior

    • start work on the north terrace

    Noise and odours are anticipated.

    If you have any questions or concerns regarding this work, please email Janet Muenzberger or call x5017 or email Lesley Owen or call x5949.

    Categories: Announcements

  • Construction update – Rankin Family Pavilion – sidewalk closure

    As part of the Rankin Family Pavilion construction project, the sidewalk on the west side of the Rankin Family Pavilion site which accesses the Tower, Thistle Complex and ScotiaBank Hall will be closed Thursday, September 20, Friday, September 21 and possibly Monday, September 24.

    If you have any questions or concerns regarding this work, please email  Scott Roper or call x4778 or email Lesley Owen or call x5949.

    Categories: Announcements

  • Construction update – Rankin Family Pavilion – September 17-21.

    As part of the Rankin Family Pavilion construction project, the following work is scheduled to occur between Monday, September 17 and Friday, September 21.

    In preparation for opening circulation from the Learning Commons to Tower Elevators and Thistle East:

    • complete installation of doors and hardware
    • complete ceiling and install lighting, mechanical and life safety devices
    • complete drywall and paintingIn other areas:
    • seal skylight joints
    • ongoing roofing including completion of 300 level at parapets
    • roofing at 200 level
    • ongoing mechanical, electrical, studding and terrazzo at 200 level
    • begin raised access floor at 300 level

    Noise and odours related to construction equipment are to be expected.

    If you have any questions or concerns regarding this work, please email  Scott Roper or call x4778 or email Lesley Owen or call x5949.

    Categories: Announcements

  • Facilities Management September Fire Alarm Bell Testing

    We are required by code to test the fire alarm systems throughout all Campus Buildings on a monthly basis.

    The test dates for this month are as follows:

    • Overnight September 16
      • 573A Glenridge Ave.
      • International Centre
      • East Academic #1, #2, and #3
      • MacKenzie Chown
      • Student Alumni Center
      • Plaza Building
      • Cairns Building
      • Goodman School of Business
    • Overnight September 17
      • Schmon Tower / Thistle Complex
      • Scotia Bank Hall
      • Welch Hall
      • Walker Complex (all)
      • South Block
      • Alphie’s Trough
    • Overnight September 18
      • Central Utilities Building
      • Kenmore Centre
      • Harrison Hall
      • B.R.I.C. (130 Lockhart)
      • Marilyn I. Walker School of Performing Arts
      • Rodman Hall (St. Paul Cres.)
      • Theal House

    For the full schedule, please follow this link. The building schedule will be the same for Sunday, Monday, and Tuesday.

     

    Categories: Announcements

  • Facilities Update – Annual Fire Alarm Testing – 573 Glenridge and the International Centre – September 17, 2018

    Contractors will be performing the annual fire alarm inspection and testing the audible devices overnight on September 17 starting at 8pm at 573 Glenridge and the International Centre.

    For any questions or concerns, please email FM@BrockU.ca or call x3717 or email Scott Kernicky or call x6201.

  • Construction update – Goodman School of Business – Monday, September 17 to Friday, September 21.

    As part of the Goodman School of Business expansion project, the following work is scheduled to start from Monday, September 17 to Friday, September 21.

    Existing Building

    • drywall contractor framing perimeter bulkheads in the perimeter offices and corridors
    • sheet metal contractor installing new fan power boxes
    • electrical contractor wiring new fan power boxes
    • flooring contractor installing ceramic tile base in the corridors
    • floor grinding from Monday Sept 17 – Thursday September 20 starting at 10:30 pm

    Noise and odours are anticipated.

    If you have any questions or concerns regarding this work, please email Janet Muenzberger or call x5017 or email Lesley Owen or call x5949.

    Categories: Announcements

  • Construction update – Rankin Family Pavilion – Sidewalk closure – September 13 & 14.

    As part of the Rankin Family Pavilion construction project, the sidewalk on the west side of the site will be closed on Thursday, September 13 and Friday, September 14 between 7:00 a.m. and 4:00 p.m. See  attached map for detour routes.

    If you have any questions or concerns regarding this work, please email  Scott Roper or call x4778 or email Lesley Owen or call x5949.

     

     

    Categories: Announcements

  • Facilities Update: Temporary Air Flow Disruption – Schmon Tower – September 10-14

    Please be advised that there may be temporary and intermittent interruption to the airflow in Schmon Tower (anticipated floors 1-6) beginning Monday September 10 to Friday September 14.  Facilities Management staff are making some modifications to the system and as a result limited amounts of air flow may be possible which may cause a slight increase in internal area temperatures.

    If you have any questions or concerns regarding this work please contact Ryan Stewart or call x3579 or Facilities Management Customer Service or call x3717.

     

  • Construction update – Rankin Family Pavilion – September 10-14.

    Please be aware that the sidewalk on the west side of the construction site will be closed for half a day next week.  Notification will be made by e-mail and on the Facilities Management website when the date is firmly scheduled.

    As part of the Rankin Family Pavilion construction project, the following work is scheduled to occur between Monday, September 10 and Friday, September 14.

    • continue to install skylight and façade glazing as material is made available
    • continue roofing as weather permits
    • continue with mechanical & electrical work and partition framing
    • for opening of corridor between Learning Commons, Tower elevators and Thistle East:
      1. Continue drywall, ceiling, terrazzo, doors, hardware and electrical work
      2. Install glazed partition at new Campus Security office

    Noise and odours related to construction equipment are to be expected.

    If you have any questions or concerns regarding this work, please email  Scott Roper or call x4778 or email Lesley Owen or call x5949.

    “Another one for Paul”

    Categories: Announcements