As part of the University Capital Plan the following Elevator Modernization Projects are ongoing;
- MC B Block – Complete modernization (KONE) – Completion scheduled for Mid May (alternate C Block)
- Tower Group – Annunciator Install (KONE) – Complete April 28, 2023
- MC C Block – Complete Modernization (KONE) – Construction start-up Mid May (Alternate B Block) – Completion End of June
- * Welch Hall – Complete Modernization (TKE) – Construction start-up Mid June (No Alternate) – Completion Mid August
- * GLN A – Complete Modernization (TKE) – Construction start-up Mid July (No Alternate) – Completion Mid September
* Please note that Welch Hall and GLN A elevators are single cars servicing their respective buildings; alternate accessibility arrangements are very limited.