Construction update – Taro Hall – Monday, Feb 12. to Friday, Feb 16.

As part of the Goodman School of Business expansion project, the following work is scheduled to start from Monday, Feb 12. to Friday, Feb 16.

West Addition

  • glazing contractor installing flashing
  • electrical contractor installing lighting
  • drywall contractor installing wood walls
  • drywall contractor taping the gallery corridor ceilings
  • floor installation in stair B
  • elevator contractor on site to prepare for final inspection
  • electrical contractor installing and commissioning the fire alarm

East Addition

  • drywall contractor framing exterior walls
  • drywall contractor taping classroom walls and ceilings
  • electrical rough-in continuing

Noise and odours are anticipated.

If you have any questions or concerns regarding this work, please email Janet Muenzberger or call x5017 or email Lesley Owen or call x5949.

 