Construction update: Schmon Tower, BrockLINC – Monday, Feb 12. to Friday, Feb 16.

As part of the Brock LINC construction project, the following work is scheduled to occur between Monday, Feb 12. and Friday, Feb. 16. 

  • cut podium waffle slab for elevator shaft
  • continue rough in for atrium lobby mechanical and electrical
  • continue rough of services at underside of podium
  • continue masonry on podium level
  • continue excavation for south frost wall
  • start forming for frost wall
  • continue wood joist and deck installation
  • measure up glazing for all sides

 Noise and odours related to construction equipment are to be expected.

If you have any questions or concerns regarding this work, please email Paul Smeltzer or x3105 or email Lesley Owen or x5949.

Construction moment of the week

Structural steel elements installed to support Level 300

 