Projects In Progress

Projects In Progress

Compiled (06/18/2013)

This report contains data from 38 Projects.


Project Number Project Name Project Status Project Manager Percent Complete

25
NHBRC - procurement and overseeing the installation of all IT related infrastructure for the building
Execution
Ed Blasinski
80%

68
Marilyn I. Walker School For Performing Arts (MIWSFPA) IT related infrastructure implementation
Initiation
Ed Blasinski
10%

75
Evergreening - Servers - 2013 - Retiring Butler
Initiation
Tom Hall
90%

81
Student Records
Execution
Alba Kotyk
80%

168
Payroll rewrite - move from LION to BrockDB
Execution
Marilou Esmores
80%

224
TPHi-ENCAMPUS Enterprise System Software research, procurement and installation
Execution
Maria Pillitteri
80%

228
Active Directory Integration of Apple Mac Computers
Initiation
Steve Biederman
0%

240
ESL Services database system development (in-house)
Execution
Maria Pillitteri
80%

254
FGS Yearly Student Progress Reports
Initiation
Maria Pillitteri
0%

277
Centralized File Storage for ALL faculty/staff/students
Execution
Michael Kuhn
75%

296
Converting the remaining pieces of the Student Information System from LION to the .net environment (BrockDB)
Execution
Mat Steglinski/Lilly Biamonte
80%

329
Evergreening - Servers - 2012 - Load Balancers
Execution
Tom Hall
25%

372
HR Forms moved to online versions with backend administrative system
Initiation
Maria Pillitteri
10%

388
Coeus Implementation for Research Services Ethics department
Execution
Maria Pillitteri
80%

390
FGS - Electronic Review of Applications for non-ISP programs
Execution
Barb Lemieux
50%

438
Pilot of ePortfolios at Brock University.
Execution
Tom Hall
90%

448
Alternative to ClockWork system in Student Development Centre
Initiation
Maria Pillitteri
10%

453
Replace the current prospective student portal & CMS licenced to Brock via EDge Interactive
Initiation
Mat Steglinski
0%

465
Evergreening - Switches - 2012 - Admin - Data Centre Programme
Initiation
Roman Cierny
0%

469
Evergreening - UPS - 2012 - Admin
Initiation
Tom Hall
50%

471
Evergreening - Cable Television - 2012 - Residences
Initiation
Tom Hall
10%

495
PCI Compliance (Network and Application Layer Penetration Testing)
Initiation
Andy Morgan
10%

499
Electronic/Online Record of Employment
Initiation
Madhu Dandamudi
0%

506
Changes to Sakai Arising from Access Copyright License
Execution
Tom Hall
50%

512
Bookstore and Brock Card integration
Initiation
Steve Alger
0%

531
MCU replacement/upgrade
Execution
Jon Winterbottom
80%

538
Cairns Building BioLinc Research Incubator Project
Execution
Ed Blasinski
20%

539
Document Repository Solution for Brock University Including Tenure and Promotion
Initiation
Des Flynn
0%

541
Evergreening - Network Appliances - 2012 - Point to Point Wireless
Initiation
Ed Blasinski
0%

552
AODA Institutional Compliance - Web Accessibility Audit
Initiation
Tom Hall
50%

553
Raiser's Edge Upgrade to latest version
Initiation
Steve Alger
0%

561
Annual update to LMS: Sakai
Initiation
Tom Hall
0%

569
Adoption of Maple TA Dept. of Mathemtics Skills Test
Execution
David Genkin
80%

574
Phase II Transfer Credits - Reports
Initiation
Norm Young
75%

581
Upgrade Structured Cabling in University Buildings 2013
Initiation
Ed Blasinski
0%

594
Experience Plus / Collegiate Link information upload and AD Authentication
Execution
Andy Morgan
10%

598
Data Centre Programme (Phase 1)
Initiation
Tom Hall
0%

601
Tenure & Promotion Electronic Submission (2013)
Initiation
Des Flynn
0%